Thursday, October 21, 2010

Brickwork started

Building is really moving - our bricks arrived on Friday and the plumbing was done on Saturday.  The Chatswood sandstocks are really beautiful and we are happy we paid the extra cost - nearly $5000.
The brickies were rained out on Tuesday so only started laying yesterday.  They are doing a very nice job  and we are very happy.  Now we just have to hope we get some fine weather for the next 2 weeks.

Wednesday, October 6, 2010

Windows and doors installed

The frame is now almost complete with the roof trusses finished.  The windows and sliding doors are all in and you can now see what kind of view we will have from the family/living area over the golf course.  Our master bedroom and ensuite also have views down the fairways.