Friday, December 3, 2010

Bricks Cleaned


The eaves were started on Tuesday and the brick cleaner arrived late afternoon.  He spent 3 hours cleaning and when he finished I had a look from inside.  It is a complete disaster - there were holes in the walls everywhere - you could see spots of daylight where he had blasted out the mortar. His blasting was so hard the concrete porch is showing the black aggregate. The bricks look terrible with bits of mortar missing everywhere. 

The wall insulation was put in on Wed morning and the carpenters only worked 3 hours and then walked off the job as the house is surrounded by a moat of water as the SS has not yet put on the downpipes, The gyprock was delivered on Thurs but no one has been back to work on the house. 

No comments:

Post a Comment